Question: Question 3 ( 8 marks ) table [ [ Task , Immediate predecessor,Task time ( min ) ] , [ 1 , - ,

Question 3(8 marks)
\table[[Task,Immediate predecessor,Task time (min)],[1,-,0.52],[2,1,0.28],[3,2,0.46],[4,1,0.3],[5,4,0.58],[6,3,5,0.48],[7,6,0.22],[8,7,0.62],[9,6,0.1],[10,6,0.38],[11,10,0.36],[12,8,9,11,0.7]]
Demand rate =120,000 units/year
Assembly operates for 50 weeks/year,6 shifts/week, and 8 hours per shift.
i. Draw a precedence diagram,
ii. Design an assembly line,
iii. Find line efficiency
iv. Total idle time in the assembly line
 Question 3(8 marks) \table[[Task,Immediate predecessor,Task time (min)],[1,-,0.52],[2,1,0.28],[3,2,0.46],[4,1,0.3],[5,4,0.58],[6,3,5,0.48],[7,6,0.22],[8,7,0.62],[9,6,0.1],[10,6,0.38],[11,10,0.36],[12,8,9,11,0.7]] Demand rate =120,000 units/year

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!