a Explain two of the basic tools of process flow analysis and highlight the limitations of each tool use examples as appropriate
marks
b Consider the jobs in the Table below. Use Moore's algorithm to find the sequence that minimizes the number of tardy jobs. Assume that processing can start at time zero.
tableJobABCDEFDue date,Processing Timk,