Question: Question 3, Chapter 15 Cost Estimation, Cost Engineering and Cost Management 3.1 Your company constructs ice plants for deep, hot mines. You recently completed an

Question 3, Chapter 15 Cost Estimation, Cost Engineering and Cost Management 3.1 Your company constructs ice plants for deep, hot mines. You recently completed an ice plant at a mine at a cost of R4,8m. This plant could produce up to 2500 tons of ice per day. Make a quick estimate of the likely cost of a new plant with a capacity of 3000 tons of ice per day. { Note: Y=0,6} 3.2 List the method/steps that you would follow to determine the cost of the plant in 3.1 to a greater degree of accuracy