Question: Question 3 (Chapter 7): Product YY is made up from parts YY1, YY2 and YY3. The master plan for product YY is given in Table

Question 3 (Chapter 7): Product YY is made up

Question 3 (Chapter 7): Product YY is made up from parts YY1, YY2 and YY3. The master plan for product YY is given in Table Q3(i). The lead time for product YY is 2 weeks and currently there is 50 units in the inventory. Table Q3(i) 1 2 3 4 7 WW Forecast 5 150 6 250 8 150 Using information in Table Q3(ii), determine the remaining inventory for parts YY1, YY2 and YY3 at the end of WW8. Part YY1 YY2 YY3 Lot size rule L4L FOQ = 100 FOQ = 250 Table Q3(ii) Lead time (weeks) Quantity for 1 unit YY 2 2 3 2 3 Beginning Inventory 0 650 100 1