Question: Question 3. Determine the slack for activity D. a. 2 days b. 4 days c. 6 days d. 5 days e. one day f. None

Question 3. Determine the slack for activity D.
a. 2 days
b. 4 days
c. 6 days
d. 5 days
e. one day
f. None
Question 4. Determine the slack for activity F.
a. 2 days
b. 3 days
c. 4 days
d. 5 days
e. 6 days
Consider the following project. Activity Immediate Processor Activity Time (days) A 6 8 A, B 5 D B 4 Timo E 7 F C D 3 G D 6 H E, F, G 5 Question 1. Determine the critical path. 1. 2.0 BCEH 3. O BDFH 4. O BDGH 5. O 6. O ABDGH None of the aboves Question 2. Determine the estimated completion time of the project. 1.0 23 days 2. O 22 days 3. 25 days 4. 24 days 5. 20 days 6. 26 daysStep by Step Solution