Question: Question 3 Dodo Sdn Bhd ordered from Koko Sdn Bhd a piece of specialised heavy equipment for its operations. Details of cost incurred are: RM
Question
Dodo Sdn Bhd ordered from Koko Sdn Bhd a piece of specialised heavy equipment
for its operations.
Details of cost incurred are:
RM
Purchase price
Import duty
Engineers fees for inspection and installation
Shipping and transport costs
Site preparation costs:
Direct labour costs
Concrete reinforcement
Maintenance and service contract for year
Dodo Sdn Bhd received a trade discount of on list price and cash
discount on early settlement. Dodo Sdn Bhd obtained a loan of RM to
finance the purchase. Interest expense on the loan for the year was RM
The equipment has a useful life of years. Dodo Sdn Bhd estimates that
dismantling cost to be RM and legal obligation to restore the site is
RM Both these values are stated in present values.
Required:
Calculate the initial cost of the plant. Your answer should explain the reasons
why some of the costs are not included in the calculation. marks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock