Question: QUESTION 3 During the contract negotiations on 12 April, Client offered to pay service provider R10 million for the design of the Ferries but service
QUESTION 3 During the contract negotiations on 12 April, Client offered to pay service provider R10 million for the design of the Ferries but service provider wanted R12 million. Client then phoned service provider on 13 April and asked them to reconsider the offer. service provider sent an email on 14 April which Client only read on 16 April. Therein service provider states that reluctantly agree to do the work for R10 million. Client phones them immediately to thank them for reconsidering the situation and also say that the contract would be ready for signature the very next day. When was agreement reached? Give reasons for your answer.