Question: QUESTION 3 Earned value 500, Planned value = 250. Actual cost-1000, Budget = 10000, Schedule = 20 Months Select the correct answer about the progress
QUESTION 3 Earned value 500, Planned value = 250. Actual cost-1000, Budget = 10000, Schedule = 20 Months Select the correct answer about the progress of the project Cannot say On Budget Under Budget Over Budget