Question: Question 3 Immediate Predecessors Activity a b m A 3 6 4 B 2 4 3 A 1 5 2 D B 4 6 5

Question 3 Immediate Predecessors Activity a b m

Question 3 Immediate Predecessors Activity a b m A 3 6 4 B 2 4 3 A 1 5 2 D B 4 6 5 E C,D 6 6 6 F DE 1 3 2 The values of a, b, and m in the table are in months. 3a) Draw the project network where Activities are On Nodes (AON). [10 marks] 3b) Determine the critical path by referring to the most likely value for the activity's duration, i.e. m. [10 marks] 3c) If the project manager wants to have a 95% chance of completing all preparations by the end of December 2025, when should the work begin? [20 marks]