Question: Question 3 Job #Due date #Remaining work days A 26 B 31 C 28 6 2 1 1 pts The table shows a group

Question 3 Job #Due date #Remaining work days A 26 B 31

Question 3 Job #Due date #Remaining work days A 26 B 31 C 28 6 2 1 1 pts The table shows a group of jobs needed to be completed at a manufacturing facility. The due date and the work days remaining to complete each job are given. Day 24 is the current date. Using the critical ratio (CR) rule, find the sequence of these jobs. What is the 2nd job in this sequence Only enter the name of the job. Ex: A)