Question: Question 3 ( Marks: 2 0 ) A project task was estimated to cost R 1 0 0 0 0 0 . A risk has
Question
Marks:
A project task was estimated to cost R
A risk has been identified that will affect the project's cost by an additional R if nothing is done to prevent the risk, the probability of this risk occurring is
Two strategies have been investigated to prevent the risk of occurring.
Strategy A would cost R to implement and has a success rate prevent the risk.
Strategy B would cost R to implement and has a success rate to prevent the risk.
Q Draw the completed decision tree for the above situation and the respective
strategies.
Q Calculate the expected cost of the strategies and do a paragraph motivation to the
sponsor on the best strategy to implement.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
