Question: Question 3 of 7 < > -/13 E Last night, the sprinkler system at Plant A was accidentally set off. The ensuing deluge destroyed



Question 3 of 7 < > -/13 E Last night, the sprinkler system at Plant A was accidentally set off. The ensuing deluge destroyed most of the cost records in Plant A for the month just completed (May). The plant manager has come to you in a panic-he has to complete his report for head office by the end of today. He wants you to give him the numbers he needs for his report. He can provide you with some fragments of information he has been able to salvage: Raw materials: Beginning $24.200 Ending 55,000 Work in process: Beginning 15,300 Finished goods: Sold in May 405,000 Ending 53,800 Manufacturing overhead: Beginning 0 Accrued wages payable: Beginning 11.600 Ending 19,400 onte ppt4.2.pptx