Question: Question 3 Project management (20 marks) Nellie is looking to upgrade and expand the research and testing area. The following information has been gathered and
Question 3 Project management (20 marks)
Nellie is looking to upgrade and expand the research and testing area. The following information has been gathered and provided to Nellie.
| Activity | Immediate predecessors | Optimistic time (weeks) | Most likely time (weeks) | Pessimistic time(weeks) | Normal Cost ($) | Crash cost ($) |
| A | 4 | 6 | 8 | 13,500 | 31,200 | |
| B | 8 | 12 | 16 | 27,000 | 62,400 | |
| C | 4 | 10 | 16 | 27,000 | 62,400 | |
| D | A | 6 | 8 | 10 | 27,000 | 46,800 |
| E | B | 12 | 14 | 16 | 27,000 | 46,800 |
| F | C | 8 | 14 | 20 | 27,000 | 78,000 |
| G | A | 2 | 10 | 18 | 54,000 | 124,800 |
| H | B | 4 | 10 | 16 | 27,000 | 78,000 |
| I | C | 6 | 10 | 14 | 40,500 | 62,400 |
| J | D, G | 4 | 4 | 4 | 6,750 | 7,800 |
| K | E, H | 8 | 8 | 8 | 6,750 | 7,800 |
| L | F | 6 | 6 | 6 | 6,750 | 7,800 |
Required:
1. Nellie is prepared to pay an additional bonus of $15,000 per day if the project is completed in 28 days. Taking into consideration the costs involved in crashing the project, should the project be reduced to 28 days to receive the bonus (show workings) (4 marks)
2.Using current literature (newspaper articles, academic journals etc), discuss some of the resource constraints that would make this upgrade and expansion challenging. Present these findings in a one-page cover letter addressed to Nellie. (5 marks)
can you please provide this two question solution only.