Question: Question 3 Project management (20 marks) Nellie is looking to upgrade and expand the research and testing area. The following information has been gathered and

Question 3 Project management (20 marks)

Nellie is looking to upgrade and expand the research and testing area. The following information has been gathered and provided to Nellie.

Activity

Immediate predecessors

Optimistic time (weeks)

Most likely time (weeks)

Pessimistic time(weeks)

Normal Cost ($)

Crash cost ($)

A

4

6

8

13,500

31,200

B

8

12

16

27,000

62,400

C

4

10

16

27,000

62,400

D

A

6

8

10

27,000

46,800

E

B

12

14

16

27,000

46,800

F

C

8

14

20

27,000

78,000

G

A

2

10

18

54,000

124,800

H

B

4

10

16

27,000

78,000

I

C

6

10

14

40,500

62,400

J

D, G

4

4

4

6,750

7,800

K

E, H

8

8

8

6,750

7,800

L

F

6

6

6

6,750

7,800

Required:

1. Nellie is prepared to pay an additional bonus of $15,000 per day if the project is completed in 28 days. Taking into consideration the costs involved in crashing the project, should the project be reduced to 28 days to receive the bonus (show workings) (4 marks)

2.Using current literature (newspaper articles, academic journals etc), discuss some of the resource constraints that would make this upgrade and expansion challenging. Present these findings in a one-page cover letter addressed to Nellie. (5 marks)

can you please provide this two question solution only.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!