Question: Question 3: Project Scheduling [28 marks] (a) Consider Table 1 that shows the schedule of testing activities of a software project. Activity ID Predecessor Duration

 Question 3: Project Scheduling [28 marks] (a) Consider Table 1 that

Question 3: Project Scheduling [28 marks] (a) Consider Table 1 that shows the schedule of testing activities of a software project. Activity ID Predecessor Duration (weeks) A NONE 5 . A 3 A 10 D B 3 E D 5 F C.E 6 G F 8 H F 1 1 G.H 5 - Table 1: Testing phase [2] [2] (a.1) Draw a Gantt chart for the above project schedule. (a.2) Draw a PERT diagram for the above project schedule. (1.3) What is the earliest completion time for the project? (a.4) What is the Slack Time of each task and each event? (2.5) What is the critical path of the project? (2.6) What would happen to the project if task C was delayed by 3 weeks? [8] [2]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!