Question: Question 3 Resource Management Project 1: Verification of a computer system The followng table shows the activities required for this project Activity ID Duration (Days)Resources

 Question 3 Resource Management Project 1: Verification of a computer system

Question 3 Resource Management Project 1: Verification of a computer system The followng table shows the activities required for this project Activity ID Duration (Days)Resources Activity 1 Test Module A 2 Test Module B 3 Test Module C 4 Test Combined Modules 5 Check User Documents 6 Print User Documents 7 Final Svstems Check 8Prepare Invoice 9|Ship to Customer mmediate Predecessor none Test Module A none Test Module B, Test Module C Test Combined Modules Check User Documents Test Combined Modules Final Systems Check Print User Documents, Final Systems Check 5 6 7 4 10 15 10 5 2 9 5 a) Draw a Gantt chart using earliest Start/Finish Times (3 marks) b) What is the critical path? (1 mark,) c) What is the minimum duration for the project? (1 mark) d) Calculate the floats for non-critical activities and show them on the chart. (2 marks) e) Develop a resource aggregation chart showing the total resource requirements for each day of the project. What is the highest fluctuation in resource demand? (3 marks) f) Now draw a Gantt chart using latest Start/Finish Times (3 marks) g) Develop a resource aggregation chart showing the total resource requirements for each day of the project. What is the highest fluctuation in resource demand? (3 marks) (h) Perform resource levelling to minimise the fluctuation in resources. Explain your solution

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!