Question: QUESTION 3 (weight 20%) A road construction project that consists of 6 activities is planned to be completed within 14 weeks. The project has a

QUESTION 3 (weight 20%) A road construction
QUESTION 3 (weight 20%) A road construction project that consists of 6 activities is planned to be completed within 14 weeks. The project has a budget based on the following estimated costs. Assume that costs are linear for each activity. Activities Measuring Blasting Filling of gravel and flattening Asphalt spreading Install light and crash barriers Install signposts and finish Estimated costs 20 000 160 000 200 000 160 000 40 000 10 000 1 2 3 4 5 6 7 8 9 10 11 12 | 13 | 14 Activity/week Measuring Blasting Filling of gravel and flattening Asphalt spreading Install light and crash barriers Install signposts and finish a) Develop a table where you summarize total cost for each week and calculate accumulated cost. What is the total planned cost for this project (the budget)? b) Find/calculate PC, AC, EV.CV. BV. SV. CPI and SPI and comment the development: After 3 weeks. Measuring is finished and Blasting vari sturt. Actual cost so far is 25 000 After 6 weeks: 50% of the Blasting activity is completed. Actual cost for this work is Afler 9 weeks: Blasting is finished, 50% of Filling of travel and flattening is complete and Install light and crash barners is finished Actual cost for all the completed work is now 350 000 11 100 000 111

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!