Question: Question 32 2 pts A certain project requires at least 28 worker-days to be completed. If there are only two workers available, what is the

Question 32 2 pts A certain project requires at
Question 32 2 pts A certain project requires at least 28 worker-days to be completed. If there are only two workers available, what is the shortest time in which the project can be completed? Assume no task requires more than one worker and that the tasks are independent of each other. 28 days More information needed 14 days 56 days