Question: Question 33 (1 point) A project is not going well. Actual costs are significantly over the Plan. A project gate review will occur in the

Question 33 (1 point) A project is not going
Question 33 (1 point) A project is not going well. Actual costs are significantly over the Plan. A project gate review will occur in the next several days. Which of the following actions would LEAST likely be considered during the review? Postpone the review until the project manager can improve cost performance Make use of the project's Management Reserve Conduct a full review of areas of high cost over-runs Terminate the project