Question: question 33 Question 33 (3.75 points) Prepare Front Iron Stitch Front & Back 5 Mins./Unit 12 Mins./Unit Prepare Back Iron 4 Mins./Unit 5 Mins./Unit 10
question 33
Question 33 (3.75 points) Prepare Front Iron Stitch Front & Back 5 Mins./Unit 12 Mins./Unit Prepare Back Iron 4 Mins./Unit 5 Mins./Unit 10 Mins./Unit 12 Mins./Unit What is the hourly utilization of the process E (Pack)? 0.5 06 01 O 12 O 0.2 Previous Page Previous Page Next Page Next Page