Question: QUESTION 34 ABC Company has developed the following linear programming problem: Max x 1 + x 2 s.t. 2x 1 + x 2 10 2x

QUESTION 34

ABC Company has developed the following linear programming problem:

Max

x1 + x2

s.t.

2x1 + x2 10

2x1 + 3x2 24

3x1 + 4x2 36

They find this problem is infeasible. In revision, the company drops the original objective and establishes three goals.

Goal 1:

Don't exceed 10 in constraint 1.

Goal 2:

Don't fall short of 36 in constraint 3.

Goal 3:

Don't exceed 24 in constraint 2.

Select the appropriate constraint for Goal 1:

a.

2x1 + x2 + d1 d1+ = 10

b.

2x1 + x2 + d1 d1+ = 10

c.

3x1 + 4x2 + d1 d1+ = 10

d.

2x1 + 3x2 + d1 d1+ = 10

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!