Question: Question 34 Consider the following activity which is a part of a network diagram: ES = 5 EF = 8 The slack for this activity

Question 34 Consider the following activity which
Question 34 Consider the following activity which is a part of a network diagram: ES = 5 EF = 8 The slack for this activity is 4 days. What are Latest Start and Latest Finish for this activity respectively? 0 2,4 9.12 12,9 5,8