Question: QUESTION 34 The following table shows the basic information for remaining stage of a late project, the minimum cost to expedite the project (shorten) by
QUESTION 34
-
The following table shows the basic information for remaining stage of a late project, the minimum cost to expedite the project (shorten) by 2 days, is to spend:
Activity
code
Preceded by
activity/ies
Normal cost, total for activity ($)
Normal Time for completion,
(days)
Crash cost, total for activity ($)
Crash Time for completion, (days)
A
B
C
D
E
F
G
H
I
-
-
A
B
B
C
A
D
E,F
200
300
400
550
450
150
470
250
250
5
6
7
9
8
3
6
5
5
300
450
500
750
500
200
600
300
300
3
5
6
7
7
2
5
4
4
150
100
200
250