Question: Question 35 (1 point) Job A38 was ordered by a customer on September 25. During the month of September, Jaycee Corporation requisitioned $2,500 of direct
Question 35 (1 point) Job A38 was ordered by a customer on September 25. During the month of September, Jaycee Corporation requisitioned $2,500 of direct materials and used $4,000 of direct labor. The job was not finished by the end of the month, but needed an additional $3,000 of direct materials and additional direct labor of $6,500 to finish the job in October. The company applies overhead at the end of each month at a rate of 200% of the direct labor cost incurred, what is the total cost of the job when it is completed in October? A) $26,500 O B) $37,000 c) $32,000 D) $22,500 E) $16,000