Question: Question 35 3 points Sa I hire you to reconstruct my restaurant for $100,000. The work is to be completed by January 1, 2022. In

Question 35 3 points Sa I hire you to reconstruct my restaurant for $100,000. The work is to be completed by January 1, 2022. In October 2021, you walk off the job and leave it unfinished. I have to hire another contractor to complete the work. He finishes the job on February 1, 2022. I have lost $10,000 in profit because my restaurant was not open. I sue you for breach of contract. The $10,000 is consequential damages The $10,000 is compensatory damages The $10,000 is cannot be sought as damages as lost business was not part of the contract None of the above