Question: Question 36 (1 point) If an activity is on a project's critical path, which of the following statements is true about that activity? ) It

 Question 36 (1 point) If an activity is on a project's

Question 36 (1 point) If an activity is on a project's critical path, which of the following statements is true about that activity? ) It is more important to the project's success than non-critical path activities )It has no predecessor activities Since it has slack time, it can be delayed without delaying the entire project's completion time. If it is delayed, the project completion time will be delayed by the same amount of D) ime Save

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!