Question: Question 36 (1 point) If an activity is on a project's critical path, which of the following statements is true about that activity? ) It
Question 36 (1 point) If an activity is on a project's critical path, which of the following statements is true about that activity? ) It is more important to the project's success than non-critical path activities )It has no predecessor activities Since it has slack time, it can be delayed without delaying the entire project's completion time. If it is delayed, the project completion time will be delayed by the same amount of D) ime Save