Question: Question 36 (6 points) A methods and measurements analyst for Timepiece, Inc., needs to develop a time standard for the task of attaching a watch

Question 36 (6 points) A methods and measurements
Question 36 (6 points) A methods and measurements analyst for Timepiece, Inc., needs to develop a time standard for the task of attaching a watch to a wristband. In a preliminary study, he observed one of his workers perform this task five times, with the following results: Observation 1 2 3 4 5 Time (secs) 27 19 27 24 29 What is the standard time for this task if the employee worked at a 10 percent faster pace than average, and an allowance of 17 percent of job time is used? (Keep two decimal places in your answer) Your