Question: Question 38 There are four activities on the critical path, and the standard deviations for their durations are 9, 19, 40, and 14 days. The

Question 38 There are four activities on the

Question 38 There are four activities on the critical path, and the standard deviations for their durations are 9, 19, 40, and 14 days. The standard deviation of the duration of the critical path is: Not yet answered a. 20.5 Marked out of 2.00 b. 2238 C. 82 P Flag question d. 47.31 e. 9.055

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!