Question: Question 39 2 pts 6 workers installed 900 square yards of carpeting in 5 hours. Find labor productivity. O 30 square yards per labor hour

Question 39 2 pts 6 workers installed 900 square

Question 39 2 pts 6 workers installed 900 square yards of carpeting in 5 hours. Find labor productivity. O 30 square yards per labor hour O 120 square yards per labor hour O 50 square yards per labor hour 900 square yards per labor hour 60 square yards per labor hour