Question: Question 4 0 ( 1 point ) There are four activities on the critical path, and they have standard deviations of 1 , 2 ,

Question 40(1 point)
There are four activities on the critical path, and they have standard deviations of 1,2,4, and 2 days. The standard deviation of the critical path is:
3
5
9
16