Question: QUESTION 4 [ 1 0 Marks ] Given below are ordinates of a stream flow hydrograph at the inlet to the new dam catchment proposed

QUESTION 4[10 Marks]
Given below are ordinates of a stream flow hydrograph at the inlet to the new dam catchment
proposed under question 2.
Calculate the following:
(a) Ordinates of direct runoff
(b) Depth of effective rainfall
(c) Ordinates of unit hydrograph
Hint: use a straight line method for base flow separation