Question: Question 4 ( 1 0 % ) : Mrs . Adams bakes cakes at home for events on a contractual basis. With just one oven,

Question 4(10%):
Mrs. Adams bakes cakes at home for events on a contractual basis. With just one oven, she faces a busy
Saturday morning when she has committed to finishing six orders. Her husband will handle deliveries, which
takes 15 minutes each. Assuming she starts baking at 7:00 A.M., she's in for a hectic day with as shown in
the following table:
Page 12 of 12
Event Time required (min) Delivery Time
17210:30 AM
2409:00 AM
313210:00 AM
43012:00 PM
518611:00 AM
6251:00 PM
a. Determine the processing sequence using each of these priority rules: First Come First Served, Shortest
Processing Time, Earliest Due Date and Critical Ratio.
b. Determine the performance of each rule using average flow time, average WIP and average days late.
Which rule is the best? Explain.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!