Question: Question 4 1 ( 2 . 0 4 1 points ) Listen The natural order between activities, where some tasks must be complete before others

Question 41(2.041 points)
Listen
The natural order between activities, where some tasks must be complete before others can begin is called
a) the critical path.
b) a precedence relationship.
C) project scheduling.