Question: Question 4 - [ 1 9 Marks ] The project manager of a marketing company has gathered the data as shown in the table below

Question 4-[19 Marks]
The project manager of a marketing company has gathered the data as shown in the table below for an advertising campaign.
\table[[Activity,Time estimates (days),}{
\table[[predecessor]]}],[Optimistic,Most likely,Pessimistic],[A,3,6,8,-],[B,2,4,4,-],[C,1,2,3,C],[D,6,7,8,B, D],[E,2,4,6,A, E],[F,6,10,14,A],[G,1,2,4,F],[H,3,6,9,G],[I,10,11,12,C],[J,14,16,20,H,I]]
(i) Draw the network.
(ii) Determine the expected completion time and variance for each activity
[6]
(iii) Calculate ES, EF, LS, LF and slack for each activity.
[4]
(iv) Determine the critical path.
[5]
(v) How long is the project likely to take?
[2]
[2]
Question 4 - [ 1 9 Marks ] The project manager of

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!