Question: Question 4 - [ 1 9 Marks ] The project manager of a marketing company has gathered the data as shown in the table below
Question Marks
The project manager of a marketing company has gathered the data as shown in the table below for an advertising campaign.
tableActivityTime estimates days
tablepredecessorOptimisticMost likely,PessimisticABCCDB DEA EFAGFHGICJHI
i Draw the network.
ii Determine the expected completion time and variance for each activity
iii Calculate ES EF LS LF and slack for each activity.
iv Determine the critical path.
v How long is the project likely to take?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
