Question: Question 4 (1 point) A project has 5 tasks, namely, A, B, C, D, and E. A, B, and C have no predecessors. C is
A project has 5 tasks, namely, A, B, C, D. and E. A, B, and C have no predocessors. C is a predecessor to D and E. As per the status date, A and B should have been completed 100%,C should have been completed 60%. Brseline cost for these tasks are: A=40,B=30,C=60,D=40, and E=10. Actual progress went as: A= 100\% finished at actual cost of 55;B=50% at Actual cost of 20;C=25% at actual cost of 25. What is the CPI? 1.2 1. 13 .8 .70