Question: Question 4 ( 1 point ) The approved budget, with contingency reserves and any amount of management reserve that has already been approved, serves as

Question 4(1 point)
The approved budget, with contingency reserves and any amount of management reserve that has already been approved, serves as a(n) for project control.
estimate
baseline
benchmark
control account