Question: Question 4 ( 1 point ) Three contractors are competing for the lowest overall bid on an A + B construction contract. The bids below

Question 4(1 point)
Three contractors are competing for the lowest overall bid on an A+B construction contract. The bids below are submitted for actual construction costs and time to construct. The owner has assessed the user delay cost at $500? calendar day. What the lowest total bid amount?
\table[[Contractor,Cost (A),Time (B)],[Contractor 1,$25200,49 Calendar Days],[Contractor 2,$25850,57 Calendar Days],[Contractor 3,$28300,48 Calendar Days]]
Your Answer: