Question: Question 4 (1 point) Which estimating method provides the most accurate estimate PERT - Program Evaluation Review technique, using optimistic, pessimestic and Most Likely estimates

Question 4 (1 point) Which estimating method provides the most accurate estimate PERT - Program Evaluation Review technique, using optimistic, pessimestic and Most Likely estimates from 3 different people Apportion method Parametric (statistical) method - example is using the time per PC upgrade from Windows 9 in a current project to upgrade to Windows 10 Bottom up estimating Question 5 (1 point) More accurate estimates can typically be obtained by using more than one Subject Matter Expert True False