Question: QUESTION 4 ( 2 0 Marks ) Answer the following questions based on resource estimate and Project Evaluation and Review Technique ( PERT ) calculations.

QUESTION 4(20 Marks) Answer the following questions based on resource estimate and Project Evaluation and Review Technique (PERT) calculations. The scope of work is to build a garage. The total size of the garage is 50 square metres. The builder knows that the work can be undertaken in 5 man-hours per square metre and the workers work a 10 hour shift. a) Calculate the man-days required. (5 Marks) b) Given the resource availability as per the table below, calculate the duration of the work to be conducted for each resource availability given. Man days Resources Available Duration 254255256257259(10 Marks) c) Different individuals that work on the project may accumulate different times to complete an activity. Based on the 4 scenarios (Estimators) of the man-days provided in the table below, calculate the PERT estimate for each scenario as well as the overall PERT Estimate Average. Estimator Best Case (days) Most Likely (days) Worst Case (days) PERT Estimate (days)1101213212131531516174161718 Average (5 Marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!