QUESTION 4(20 Marks)
Care Construction Pvt Ltd has been awarded a contract to build a new office complex for a multinational corporation in a
bustling urban area. The project is slated to begin in three months and the activities are provided for below.
Activity Preceding
Optimistic
Time
Probable
Time
Pessimistic
Time
A --71019
B A 228
C A 81216
D A 3510
E B 468
F B 6810
G C, F 234
H D 228
I H 6816
J G, I 4614
K E, J 258
You have been asked by the project manager to assist in determining the following.
a) The activities that are critical for the project and should not be delayed.
b) Determine the expected completion time of each of the project activities.
c) Determine the estimated time of completion of the project.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!