Question: Question 4 ( 2 . 5 points ) A firm is considering two projects. Both projects will cost $ 5 , 0 0 0 .

Question 4(2.5 points)
A firm is considering two projects. Both projects will cost $5,000. However, Project 1 will generate cash flows of $2,500 at. the end of the first year and $7,500 at the end of the second year and Project 2 will generate cash flows of $7,500 at the end of the first year and $2,500 at the end of the second year. Which project has the highest net present value if the required rate of return is 10%?
Project 1
Project 2
Both projects have the same net present value.
Cannot determine from information given.