Question: Question 4 2 A company is designing a product layout for a new product. It plans to use this production line eight hours a day
Question A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet projected demand of units per day. The tasks necessary to produce this product are:TaskImmediateTimesecsPredecessornoneVYIf the company wants the output rate to be equal to demand, what is the last task performed at the second workstation if tasks are assigned in order of the most following tasks first? Break ties using the longest task timeie if a task has longer task time. assign that task firstO uO VO w