Question: Question 4 ( 2 points ) A contractor accepts a project, after go - ahead, and the contractor discovers that the statement of work was
Question points
A contractor accepts a project, after
goahead, and the contractor
discovers that the statement of work
was illdefined and pushed through
scope changes that significantly
alienate the customer. The customer
pays for the scope changes and then
files a law suit against the contractor
to recover the cost of the scope
changes. Neglecting the type of
contract, the court would most likely
rule that: pts
The contractor is at fault for
accepting a contract with ill
defined requirements and nc
discovering this initially.
Step by Step Solution