Question: Question 4 (20 marks). Complete the following analysis for the project detailed as Question #13 from the end-of-chapter problems for Chapter 17. For the 6th
Question 4 (20 marks). Complete the following analysis for the project detailed as Question #13 from the end-of-chapter problems for Chapter 17. For the 6th edition of the text, Question #13 is on page 706, for the 5th edition of the text it is on page 717.
(a) Sketch a precedence network diagram to depict the project activities. (3 marks)
(b) Complete a forward and backward pass to determine the ES, EF, LS and LF times for each project activity. (5 marks)
(c) Determine the critical path and establish the minimum amount of time complete the entire project without crashing. (3 marks)
(d) Which activities have slack, and how much? What paths have slack and how much? (3 marks)
(e) Determine the minimum-cost crashing schedule that will reduce the total length of the project by five weeks; which activities should you shorten (crash) and by how much. (6 marks)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
