Question: Question 4 (25 points) An activity graph for a software development project is shown in Figure 1. The number corresponding to each edge of the
Question 4 (25 points) An activity graph for a software development project is shown in Figure 1. The number corresponding to each edge of the graph indicates the number of days required to complete the activity represented by that branch. Create a Table showing the Activity, EST, and LST and Slack Find the critical path. What is the minimum time the project will take to complete? START A LFINISH Figure An activity graph for a software development project Activit EST LST Slack B..C B..F B..D C..E E..H E.F D..G G.I K..L H..L