Question: Question 4 (25 pts) A task was baselined at 6 hours, but 3 hours have been spent and the estimate to complete is 3
Question 4 (25 pts) A task was baselined at 6 hours, but 3 hours have been spent and the estimate to complete is 3 additional hours. The task was to have been completed already. Assume an Hourly Rate of $180 per hour. a. Calculate: PV, AC, EV, SV, CV, BAC, CPI, SPI (15 pts)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts