Question: QUESTION 4 [ 3 0 ] To test how effectively the website and mobile app can facilitate the activities of the hunger relief programme, 1

QUESTION 4[30]
To test how effectively the website and mobile app can facilitate the activities of the hunger relief
programme, 100 smartphones with the installed app are in the process of being issued to
beneficiaries located in the East Rand of Johannesburg. The budget at completion (BAC) for
procuring and distributing the smartphones and training the beneficiaries on using the app is
estimated at R50,000.00 and scheduled over 30 days. The work performed every 10 days is
budgeted at a planned value (PV) of R16,667.00. By the end of day 10, R12,500.00 has been
spent while 28% of the work has been completed.
4.1. Calculate the earned value (EV) by the end of day 10.(4)
4.2. Calculate the cost variance (CV) by the end of day 10.(4)
4.2.1. What does the CV calculated in Question 4.2 indicates about the cost of
performing the work? (1)
4.3. Calculate the schedule variance (SV) by the end of day 10.(4)
4.3.1. What does the SV calculated in Question 4.3 indicates about the duration of
performing the work? (1)
4.4. Calculate the cost performance index (CPI) by the end of day 10.(4)
4.4.1. What does the CPI that you calculated in Question 4.4 indicates about the project
budget? (1)
4.5. Calculate the schedule performance index (SPI) by the end of day 10.(4)
4.5.1. What does the SPI that you calculated in Question 4.5 indicates about the project
schedule? (1)
4.6. Calculate the estimate at completion (EAC) in terms of cost.(4)
4.7. Calculate the EAC in terms of time.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!