Question: Question 4 3 1 pts Given the following project network, what is the impact on the critical path and project duration if activity H is

Question 43
1 pts
Given the following project network, what is the impact on the critical path and project duration if activity H is delayed by a week?
A) Both the critical path and project duration remain the same.
b) the critical path remains the same, but the project duration becomes 25 weeks.
c) the critical path remains the same, but the project duration increases by 1 week.
d) the critical path changes to B-C-G-H-J-K, and the project duration becomes 19 weeks.
e) the critical path changes to B-C-D-H-J-K, and the project duration becomes 21 weeks.
 Question 43 1 pts Given the following project network, what is

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!