Question: Question 4 3 1 pts Given the following project network, what is the impact on the critical path and project duration if activity H is
Question
pts
Given the following project network, what is the impact on the critical path and project duration if activity is delayed by a week?
A Both the critical path and project duration remain the same.
b the critical path remains the same, but the project duration becomes weeks.
c the critical path remains the same, but the project duration increases by week.
d the critical path changes to and the project duration becomes weeks.
e the critical path changes to and the project duration becomes weeks.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
