Question: Question 4 ( 4 0 % ) : A new road section with concrete pavement, shown in longitudinal section as Figure 1 , is 1

Question 4(40%) :
A new road section with concrete pavement, shown in longitudinal section as Figure 1, is
11,600 feet long. It is to be constructed in accordance with the following conditions:
The balanced earthworks from station 00 to 58(00) may be done at the same
time as the balanced earthworks from station 58(00) to 116(00) using two
separate independent crews.
The double-box culvert will be built by one crew, and another crew will be build
the two small culverts. Concrete may be supplied either from the paving batch
plant or from small independent mixers at the culvert sites, whichever is
expedient.
One small slip-form paver will do all the concrete paving work, and all the
shouldering will then follow with one crew after the concrete pavement is cured.
Seeding the embankments with grass must be left as late as possible.
The activities of the project are listed in Table 1. For the road project as described
above:
Develop a WBS with your own coding system (DO NOT follow the
MasterFormat as it is not a building project) and present it in a hierarchical
graph; and
Prepare an AON network diagram and perform a CPM analysis. With respect
******* Please take your time and anser it correctly **************to the task order and IPA's, you must use t
missing sequences - remember to state your assumptions. Find the minimum
project duration, identify the critical path, and calculate the activities times (ES,
EF,LS,LF,TF,FF). The unit of the duration in the activity table is days.
Question 4 ( 4 0 % ) : A new road section with

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!