Question: QUESTION 4 4 . 1 An operator working on a press produces 8 1 0 pieces in an eight hour shift. The company has a

QUESTION 4
4.1 An operator working on a press produces 810 pieces in an eight hour shift. The company has a standard rate of 0.76 minutes per piece for the drilling press.
4.2.1 How many standard hours does the operator earn?
(3)
4.2.2 What is the operator's efficiency on this shift?
(3)
4.2.3 If a base rate is R28,80 per hour, calculate the operator's earnings for the day.
(3)
-4-
DEFACJO
ASSESSMENT 1: 2024
4.2.4 Calculate the standard piece cost (cost per piece).
(3)
4.2.5 What is the direct labour cost per piece using the operator's efficiency?
(3)
4.2.6 Why is there a discrepancy between the standard piece cost and the piece cost at the operator's efficiency and what are the implications of these varying piece costs on the profitability of the organisation?
Question 5
5.1 Consider the assembly line network below. The assembly line operations (A to G) indicate their processing times in minutes. Productive time is 52 minutes and demand 400 units per hour.
5.1.1 Optimize the above assembly line by balancing the line.
(20)
[20]
 QUESTION 4 4.1 An operator working on a press produces 810

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!