Question: Question 4 a) Discuss the six (6) steps basic to both PERT and CPM [12 marks] b) Consider the network presented in the following table.

Question 4 a) Discuss the six (6) steps basic to

Question 4 a) Discuss the six (6) steps basic to both PERT and CPM [12 marks] b) Consider the network presented in the following table. Calculate 1. All possible paths II. The critical path III. The slack available at any non-critical points IV. The minimum project duration Duration (Days) 5 3 Task A B D E - Immediate Predecessors None A A B,D 2 1 [8 marks]